Construction and development monitoring of allotted industrial units across all sectors of Bin Qasim Industrial Park — Special Economic Zone. Milestone tracking, physical progress verification and Certificate of Completion issuance as at 05 October 2026.
Physical progress against approved building plans, top allottees
Health of the 236 units currently under construction
Planned construction window by project, FY 2025-26 to H1 FY 2026-27
Milestones past their approved date requiring monitoring intervention
M/s Karachi Chemicals Ltd — Boundary Wall
Missed by 86 days. Site remains unfenced; possession dispute with adjacent allottee unresolved. Certificate of Completion application blocked.
M/s Silicon Electronics — Foundation
Missed by 75 days. Revised structural drawings under review by the consultant; no mobilisation on site since July 2026.
M/s Al-Habib Steel Mills — Machinery Installation
Missed by 48 days. Import clearance for two press lines pending at Karachi Port; revised commissioning date advised as 28 November 2026.
M/s Falcon Textiles (Pvt) Ltd — Structural Frame
Missed by 43 days. Labour shortage at the contractor's sub-vendor in SITE area; revised programme submitted and accepted.
Milestone-wise planned, actual and forecast dates with current delay position
| Project / Allottee | Plot | Milestone | Planned Date | Actual / Forecast | Progress | Delay (days) | Status | Action |
|---|---|---|---|---|---|---|---|---|
|
ZP
M/s Zenith Polymer Industries Plot A-22 · Sector A |
Plot A-22 · Sector A | Structural Frame | 30 Aug 2026 | 04 Sep 2026 |
58%
|
5 | Delayed | |
|
DF
M/s Delta Foods (Pvt) Ltd Plot C-07 · Sector C |
Plot C-07 · Sector C | Roof Slab | 15 Sep 2026 | 12 Sep 2026 |
76%
|
0 | On Schedule | |
|
FT
M/s Falcon Textiles (Pvt) Ltd Plot B-14 · Sector B |
Plot B-14 · Sector B | Foundation | 20 Jul 2026 | 18 Jul 2026 |
92%
|
0 | On Schedule | |
|
OP
M/s Orbit Pharmaceuticals Plot C-18 · Sector C |
Plot C-18 · Sector C | Machinery Installation | 30 Jun 2026 | 02 Jul 2026 |
100%
|
2 | Completed | |
|
ME
M/s Metro Engineering Works Plot D-05 · Sector D |
Plot D-05 · Sector D | Site Levelling | 25 Sep 2026 | 25 Sep 2026 |
64%
|
0 | On Schedule | |
|
KC
M/s Karachi Chemicals Ltd Plot A-08 · Sector A |
Plot A-08 · Sector A | Boundary Wall | 10 May 2026 | 04 Aug 2026 |
100%
|
86 | Critical | |
|
SE
M/s Silicon Electronics Plot E-03 · Sector E |
Plot E-03 · Sector E | Foundation | 01 Aug 2026 | 15 Oct 2026 |
34%
|
75 | Critical | |
|
NL
M/s NorthStar Logistics Plot E-11 · Sector E |
Plot E-11 · Sector E | Certificate of Completion | 31 Aug 2026 | 05 Sep 2026 |
100%
|
5 | Completed | |
|
IA
M/s Indus Auto Parts Plot B-27 · Sector B |
Plot B-27 · Sector B | Trial Production | 20 Oct 2026 | 18 Nov 2026 |
41%
|
29 | Delayed | |
|
CP
M/s Crescent Packaging Plot D-12 · Sector D |
Plot D-12 · Sector D | Land Possession | 01 Sep 2026 | 01 Sep 2026 |
100%
|
0 | Completed | |
|
AH
M/s Al-Habib Steel Mills Plot A-31 · Sector A |
Plot A-31 · Sector A | Machinery Installation | 10 Sep 2026 | 28 Oct 2026 |
47%
|
48 | Critical | |
|
PC
M/s Pak Ceramics Plot C-25 · Sector C |
Plot C-25 · Sector C | Roof Slab | 05 Oct 2026 | 05 Oct 2026 |
55%
|
0 | On Schedule | |
|
SA
M/s Sindh Agri Processing Plot B-33 · Sector B |
Plot B-33 · Sector B | Site Levelling | 01 Nov 2026 | Forecast 01 Nov 2026 |
0%
|
0 | Not Started | |
|
GA
M/s Global Auto Components Plot D-19 · Sector D |
Plot D-19 · Sector D | Foundation | 30 Sep 2026 | 06 Oct 2026 |
38%
|
6 | Delayed | |
|
ZP
M/s Zenith Polymer Industries Plot A-22 · Sector A |
Plot A-22 · Sector A | Machinery Installation | 15 Nov 2026 | Forecast 15 Nov 2026 |
0%
|
0 | Not Started | |
|
DF
M/s Delta Foods (Pvt) Ltd Plot C-07 · Sector C |
Plot C-07 · Sector C | Utility Connection | 20 Nov 2026 | Forecast 20 Nov 2026 |
0%
|
0 | Not Started | |
|
FT
M/s Falcon Textiles (Pvt) Ltd Plot B-14 · Sector B |
Plot B-14 · Sector B | Structural Frame | 10 Aug 2026 | 22 Sep 2026 |
68%
|
43 | Delayed | |
|
OP
M/s Orbit Pharmaceuticals Plot C-18 · Sector C |
Plot C-18 · Sector C | Certificate of Completion | 28 Sep 2026 | 27 Sep 2026 |
100%
|
0 | Completed |
No construction milestones match the current filters.
Issued to allottees whose units passed final inspection
| Certificate No. | Allottee | Plot | Issue Date | Issued By | Status | Action |
|---|---|---|---|---|---|---|
| BQIP-COC-2026-0148 | M/s Orbit Pharmaceuticals Unit 4 · Pharmaceuticals |
Plot C-18 · Sector C | 27 Sep 2026 | Nadia Bukhari | Issued | |
| BQIP-COC-2026-0146 | M/s NorthStar Logistics Unit 2 · Logistics |
Plot E-11 · Sector E | 05 Sep 2026 | Nadia Bukhari | Issued | |
| BQIP-COC-2026-0144 | M/s Delta Foods (Pvt) Ltd Unit 7 · Food Processing |
Plot C-07 · Sector C | 18 Sep 2026 | Bilal Ahmed | Dispatched | |
| BQIP-COC-2026-0141 | M/s Metro Engineering Works Unit 1 · Engineering |
Plot D-05 · Sector D | 22 Aug 2026 | Nadia Bukhari | Issued | |
| BQIP-COC-2026-0138 | M/s Crescent Packaging Unit 3 · Packaging |
Plot D-12 · Sector D | 09 Aug 2026 | Bilal Ahmed | Dispatched | |
| BQIP-COC-2026-0151 | M/s Pak Ceramics Unit 1 · Ceramics |
Plot C-25 · Sector C | 02 Oct 2026 | Bilal Ahmed | Pending Signature | |
| BQIP-COC-2026-0132 | M/s Zenith Polymer Industries Unit 2 · Chemicals |
Plot A-22 · Sector A | 30 Jul 2026 | Nadia Bukhari | Issued | |
| BQIP-COC-2026-0152 | M/s Global Auto Components Unit 1 · Automotive |
Plot D-19 · Sector D | 04 Oct 2026 | Bilal Ahmed | Pending Signature |
Physical verification by the Monitoring Wing