Project Progress

Construction and development monitoring of allotted industrial units across all sectors of Bin Qasim Industrial Park — Special Economic Zone. Milestone tracking, physical progress verification and Certificate of Completion issuance as at 05 October 2026.

Updated 05 Oct 2026, 09:15 PKT
Under Construction
236
Units with active works
On Schedule
148
Within approved timeline
Delayed
51
Beyond planned milestone
Completed
234
Operational units
Avg. Completion
68.4%
Across active units
CoC Issued
148
Certificates of Completion
Construction Completion by Allottee

Physical progress against approved building plans, top allottees

All plots
Construction Status

Health of the 236 units currently under construction

236
Under Construction
On Schedule 148 Delayed 51 Critical 37
Completed Units234
Avg. Completion68.4%
Certificates Issued148
Construction Timeline — Programmed vs Actual

Planned construction window by project, FY 2025-26 to H1 FY 2026-27

Bars show planned duration
Jul 25
Aug 25
Sep 25
Oct 25
Nov 25
Dec 25
Jan 26
Feb 26
Mar 26
Apr 26
May 26
Jun 26
Jul 26
Aug 26
Sep 26
Oct 26
Nov 26
Dec 26
M/s Zenith Polymer Industries
Delayed
M/s Delta Foods (Pvt) Ltd
On Schedule
M/s Falcon Textiles (Pvt) Ltd
Delayed
M/s Karachi Chemicals Ltd
Critical
M/s NorthStar Logistics
Completed
M/s Orbit Pharmaceuticals
Completed
M/s Metro Engineering Works
On Schedule
M/s Silicon Electronics
Critical
M/s Al-Habib Steel Mills
Critical
M/s Global Auto Components
Delayed
On Schedule Completed Delayed Critical

Delay Alerts

Milestones past their approved date requiring monitoring intervention

Delay Report

M/s Karachi Chemicals Ltd — Boundary Wall

Missed by 86 days. Site remains unfenced; possession dispute with adjacent allottee unresolved. Certificate of Completion application blocked.

M/s Silicon Electronics — Foundation

Missed by 75 days. Revised structural drawings under review by the consultant; no mobilisation on site since July 2026.

M/s Al-Habib Steel Mills — Machinery Installation

Missed by 48 days. Import clearance for two press lines pending at Karachi Port; revised commissioning date advised as 28 November 2026.

M/s Falcon Textiles (Pvt) Ltd — Structural Frame

Missed by 43 days. Labour shortage at the contractor's sub-vendor in SITE area; revised programme submitted and accepted.

Construction Milestones

Milestone-wise planned, actual and forecast dates with current delay position

0 records Plot Register
Project / Allottee Plot Milestone Planned Date Actual / Forecast Progress Delay (days) Status Action
ZP
M/s Zenith Polymer Industries
Plot A-22 · Sector A
Plot A-22 · Sector A Structural Frame 30 Aug 2026 04 Sep 2026
58%
5 Delayed
DF
M/s Delta Foods (Pvt) Ltd
Plot C-07 · Sector C
Plot C-07 · Sector C Roof Slab 15 Sep 2026 12 Sep 2026
76%
0 On Schedule
FT
M/s Falcon Textiles (Pvt) Ltd
Plot B-14 · Sector B
Plot B-14 · Sector B Foundation 20 Jul 2026 18 Jul 2026
92%
0 On Schedule
OP
M/s Orbit Pharmaceuticals
Plot C-18 · Sector C
Plot C-18 · Sector C Machinery Installation 30 Jun 2026 02 Jul 2026
100%
2 Completed
ME
M/s Metro Engineering Works
Plot D-05 · Sector D
Plot D-05 · Sector D Site Levelling 25 Sep 2026 25 Sep 2026
64%
0 On Schedule
KC
M/s Karachi Chemicals Ltd
Plot A-08 · Sector A
Plot A-08 · Sector A Boundary Wall 10 May 2026 04 Aug 2026
100%
86 Critical
SE
M/s Silicon Electronics
Plot E-03 · Sector E
Plot E-03 · Sector E Foundation 01 Aug 2026 15 Oct 2026
34%
75 Critical
NL
M/s NorthStar Logistics
Plot E-11 · Sector E
Plot E-11 · Sector E Certificate of Completion 31 Aug 2026 05 Sep 2026
100%
5 Completed
IA
M/s Indus Auto Parts
Plot B-27 · Sector B
Plot B-27 · Sector B Trial Production 20 Oct 2026 18 Nov 2026
41%
29 Delayed
CP
M/s Crescent Packaging
Plot D-12 · Sector D
Plot D-12 · Sector D Land Possession 01 Sep 2026 01 Sep 2026
100%
0 Completed
AH
M/s Al-Habib Steel Mills
Plot A-31 · Sector A
Plot A-31 · Sector A Machinery Installation 10 Sep 2026 28 Oct 2026
47%
48 Critical
PC
M/s Pak Ceramics
Plot C-25 · Sector C
Plot C-25 · Sector C Roof Slab 05 Oct 2026 05 Oct 2026
55%
0 On Schedule
SA
M/s Sindh Agri Processing
Plot B-33 · Sector B
Plot B-33 · Sector B Site Levelling 01 Nov 2026 Forecast 01 Nov 2026
0%
0 Not Started
GA
M/s Global Auto Components
Plot D-19 · Sector D
Plot D-19 · Sector D Foundation 30 Sep 2026 06 Oct 2026
38%
6 Delayed
ZP
M/s Zenith Polymer Industries
Plot A-22 · Sector A
Plot A-22 · Sector A Machinery Installation 15 Nov 2026 Forecast 15 Nov 2026
0%
0 Not Started
DF
M/s Delta Foods (Pvt) Ltd
Plot C-07 · Sector C
Plot C-07 · Sector C Utility Connection 20 Nov 2026 Forecast 20 Nov 2026
0%
0 Not Started
FT
M/s Falcon Textiles (Pvt) Ltd
Plot B-14 · Sector B
Plot B-14 · Sector B Structural Frame 10 Aug 2026 22 Sep 2026
68%
43 Delayed
OP
M/s Orbit Pharmaceuticals
Plot C-18 · Sector C
Plot C-18 · Sector C Certificate of Completion 28 Sep 2026 27 Sep 2026
100%
0 Completed

No construction milestones match the current filters.

Certificates of Completion

Issued to allottees whose units passed final inspection

Certificate No. Allottee Plot Issue Date Issued By Status Action
BQIP-COC-2026-0148
M/s Orbit Pharmaceuticals
Unit 4 · Pharmaceuticals
Plot C-18 · Sector C 27 Sep 2026 Nadia Bukhari Issued
BQIP-COC-2026-0146
M/s NorthStar Logistics
Unit 2 · Logistics
Plot E-11 · Sector E 05 Sep 2026 Nadia Bukhari Issued
BQIP-COC-2026-0144
M/s Delta Foods (Pvt) Ltd
Unit 7 · Food Processing
Plot C-07 · Sector C 18 Sep 2026 Bilal Ahmed Dispatched
BQIP-COC-2026-0141
M/s Metro Engineering Works
Unit 1 · Engineering
Plot D-05 · Sector D 22 Aug 2026 Nadia Bukhari Issued
BQIP-COC-2026-0138
M/s Crescent Packaging
Unit 3 · Packaging
Plot D-12 · Sector D 09 Aug 2026 Bilal Ahmed Dispatched
BQIP-COC-2026-0151
M/s Pak Ceramics
Unit 1 · Ceramics
Plot C-25 · Sector C 02 Oct 2026 Bilal Ahmed Pending Signature
BQIP-COC-2026-0132
M/s Zenith Polymer Industries
Unit 2 · Chemicals
Plot A-22 · Sector A 30 Jul 2026 Nadia Bukhari Issued
BQIP-COC-2026-0152
M/s Global Auto Components
Unit 1 · Automotive
Plot D-19 · Sector D 04 Oct 2026 Bilal Ahmed Pending Signature
Recent Site Visits

Physical verification by the Monitoring Wing

M/s Delta Foods (Pvt) Ltd — Plot C-07 · Sector C
04 Oct 2026 · Bilal Ahmed (Monitoring Officer)
Roof slab curing complete; internal plaster 60% done. Utility trenching to commence 12 Oct 2026.
M/s Falcon Textiles (Pvt) Ltd — Plot B-14 · Sector B
03 Oct 2026 · Hamza Tariq (Plot Officer)
Structural frame progressing but steel fixing behind programme. Contractor advised to add a second gang.
M/s Karachi Chemicals Ltd — Plot A-08 · Sector A
01 Oct 2026 · Bilal Ahmed (Monitoring Officer)
No activity observed on site. Boundary wall incomplete; allottee's representative not available.
M/s Orbit Pharmaceuticals — Plot C-18 · Sector C
28 Sep 2026 · Nadia Bukhari (SEZ Committee)
Final inspection passed. Machinery commissioned and trial run successful; Certificate of Completion recommended.
M/s Sindh Agri Processing — Plot B-33 · Sector B
26 Sep 2026 · Hamza Tariq (Plot Officer)
Possession handed over. Site pegs verified; levelling contractor to mobilise by 01 Nov 2026.